  227.556.  Revised project plan required, when. — 1.  If, prior to the letting date of the construction project, the commission's project plan is changed so that additional or different utility relocation work is found necessary, the commission shall furnish a revised project plan under section 227.554, and the owner shall provide the commission with a revised relocation plan under section 227.555, except that the time allowed for the owner to submit the revised relocation plan after receipt of the revised project plan shall not exceed sixty days.

  2.  If, after the letting date of the highway construction project, additional utility relocation work is found necessary which was not indicated on the original project plan, the commission shall provide the owner with a revised project plan within fifteen days and the commission and the owner shall agree on a reasonable schedule for completion of the additional utility location.

­­--------

(L. 2005 H.B. 209 § 227.246)

Effective 1-01-06


---- end of effective  01 Jan 2006 ----

use this link to bookmark section  227.556


Click here for the Reorganization Act of 1974 - or - Concurrent Resolutions Having Force & Effect of Law
In accordance with Section 3.090, the language of statutory sections enacted during a legislative session are updated and available on this website on the effective date of such enacted statutory section. Revisor Home    

Other Information
 Recent Sections Editorials May Be Cited As Tables & Forms Multiple Enact
Repeal & Transfer Definitions End Report

Site changes Pictures Contact

Other Links
Legislative Research Oversight MOLIS
Library MO WebMasters
Senate
Missouri Senate
State of Missouri
MO.gov
House
Missouri House